Construct new water storage tank, upgrade wellhead, pump, control and electrical systems.
Location
Chiloquin Ranger Station
Project timeline
1
Scoping Start
04/02/2004
2
Comment Period
04/13/2004
3
Decision
05/2004 (Estimated)
4
Implementation
07/2004 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Facility Improvements/Construction |
| Chiloquin Ranger Station Water System Reconstruction | Decision Signed Date: 05/05/2004 |
| Forests | Fremont-Winema National Forest |
| Districts | Chiloquin Ranger District |
| Legal Land Description | T34S, R7.5E, Section 33 |