OPB has proposed to install an 8'(high) by 6' (long) by 4' (wide) metal equipment cabinet next to OPB's existing microwave repeater towers.
Location
Cox Peak Communications Site
Project timeline
1
Scoping Start
02/24/2014
2
Decision
06/2014 (Estimated)
3
Implementation
06/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Oregon Public Broadcasting Cox Peak Communication Upgrade | Decision Signed Date: 06/16/2014 |
| Forests | Fremont-Winema National Forest |
| Districts | Lakeview Ranger District |
| Legal Land Description | T37S, R20E, WM, section 4 SE1/4NW1/4 |