The purposes of this project, consistent with the Winema National Forest Land and Resource Management Plan, is to promote the overall sustainability of vegetative systems and hydrologic functioning within the project planning area.
Location
South Chiloquin
Project timeline
1
NOI in Federal Register
10/15/2015
2
DEIS NOA in Federal Register
07/07/2017
3
FEIS NOA in Federal Register
06/29/2018
4
Objection Period Start
03/30/2018
5
Decision
08/2018 (Estimated)
6
Implementation
09/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Heritage Resource Management; Special Products Sales; Noxious Weed Treatments; Road Maintenance; Road Improvements/Construction; Travel Management; Timber Sales (Green); Watershed Improvements |
| Lobert Restoration Project | Decision Signed Date: 08/21/2018 |
| Forests | Fremont-Winema National Forest |
| Districts | Chiloquin Ranger District |
| Legal Land Description | T 33S R7.5E S 13, 14, 15, 22, 23, 24, 25, 26, 35, 36 T33S R 7E S 12, 13, 15, 16, 18, 19, 21, 22, 23, 24, 25, 26,27, 28, 29, 30, 31, 32, 33, 34, 35, 36 T33S R8E S 7, 8, 17, 18, 19, 20, 29, 30, 31 |