Harvest of dead trees adjacent to 2 miles of FSR 4550 and several short spurs. Total acres is 249.
Location
The Project is located adjacent to FSR 4550 and several of its spurs (4550-260, 4550-263, 4550-290, 4550-330, 4550-360, and 4550-489), approximately 25 miles east of the City of Chiloquin.
Project timeline
1
Scoping Start
04/25/2018
2
Decision
11/2018 (Estimated)
3
Implementation
04/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Special Products Sales; Timber Sales (Salvage) |
| Road 4550 Commercial Firewood | Decision Signed Date: 11/29/2018 |
| Forests | Fremont-Winema National Forest |
| Districts | Chiloquin Ranger District |
| Legal Land Description | Not Applicable |