The project proposes to decommission about 3.5 miles of system roads that are currently in maintenance level 1 (closed to all access), for the purpose of improving watershed conditions.
Location
The project is located about 45 miles northwest of Klamath Falls, OR; off of Westside Road, adjacent to Upper Klamath Lake.
Project timeline
1
Scoping Start
05/18/2018
2
Comment Period
08/12/2018
3
Objection Period Start
09/23/2018
4
Decision
11/2018 (Estimated)
5
Implementation
11/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Travel Management; Watershed Improvements |
| Sevenmile Creek Road Decommissioning | Decision Signed Date: 11/16/2018 |
| Forests | Fremont-Winema National Forest |
| Districts | Klamath Ranger District |
| Legal Land Description | T33S, R06E, Sections 9, 10, 11, 14, 16, 17, 21, 26, and 27 |