The proposed project is to relocate the headbox to the new Horseglades Spring source and install a new pipeline to the relocated watering trough.
Location
Horseglades Spring
Project timeline
1
Scoping Start
12/09/2020
2
Decision
06/2021 (Estimated)
3
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management |
| Horseglades Spring Repair and Trough Relocation | Decision Signed Date: 06/25/2021 |
| Forests | Fremont-Winema National Forest |
| Districts | Bly Ranger District |
| Legal Land Description | Not Applicable |