The Fremont Winema NF is proposing to decommission approximately 3.1 miles of the 4020303 road along the east side of Dog Lake due to poor road conditions, hydrological issues, unstable soils, danger trees, and repeated need for maintenance
Location
The Project is east of Dog Lake, approximately 19 miles southwest of the town of Lakeview in Sections 22, 27, and 33-34 of, T40S, R17E; Lake County, Oregon.
Project timeline
1
Scoping Start
02/02/2021
2
Decision
07/2022 (Estimated)
3
Implementation
07/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning |
| Forests | Fremont-Winema National Forest |
| Districts | Lakeview Ranger District |
| Legal Land Description | Not Applicable |