Decision Memo Completed

Fuller Walker Timber Bridge Repairs with Thermoplastic Components

Fremont-Winema National Forest Lake, Oregon Paisley Ranger District

Fuller Walker bridge is suffering decay that is nearly at critical finding levels, which would prohibit vehicle use. This project will replace failing timber members with innovative thermoplastic members to allow for continued and unrestricted use.

Location

T 34S, R 16E, S 20

Project timeline

1
Scoping Start
03/17/2021
2
Decision
04/2021 (Estimated)
3
Implementation
04/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Fuller Walker Timber Bridge Repairs with Thermoplastic ComponentsDecision Signed Date: 04/20/2021
ForestsFremont-Winema National Forest
DistrictsPaisley Ranger District
Legal Land DescriptionNot Applicable
Road management