Decision Memo Completed

U of O Applegate Butte Seismic Monitoring Site Project

Fremont-Winema National Forest Klamath, Oregon Chiloquin Ranger District

The Pacific Northwest Seismic Network wants to install an Earthquake Early Warning Station consisting of three structures. Applegate Butte will provide a key location to fill a gap within the earthquake warning network.

Location

The seismic monitor will be located on top of Applegate Butte, Chiloquin Ranger District.

Project timeline

1
Scoping Start
04/26/2022
2
Decision
08/2022 (Estimated)
3
Implementation
09/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
U of O Applegate Butte Seismic Monitoring Site ProjectDecision Signed Date: 08/02/2022
ForestsFremont-Winema National Forest
DistrictsChiloquin Ranger District
Legal Land DescriptionT. 33 S., R. 8 E., Sec. 13
Special use management