Decision Memo Completed

Dump Hill Mastication

Fremont-Winema National Forest Klamath, Oregon Chiloquin Ranger District

I am proposing a fuels reduction treatment in the Dump Hill project area. Fuels treatments will include the removal of brush and small trees up to 4 inch DBH. Timeframe for implementation is Spring 2024.

Location

The Dump Hill Project area is located East of the town of Chiloquin, OR and South of the Sprague River Road.

Project timeline

1
Scoping Start
07/26/2022
2
Decision
01/2024 (Estimated)
3
Implementation
05/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels)
Dump Hill MasticationDecision Signed Date: 01/16/2024
ForestsFremont-Winema National Forest
DistrictsChiloquin Ranger District
Legal Land DescriptionT. 34S., R. 7E., Sec. 35
Fuels management