PacifiCorp wants to add a junction box along their line to provide electricity to thye GTN Pipeline to support their anode system which protects the pipeline.
Location
This project is located on the Chiloquin Ranger District, Fremont-Winema National Forest.
Project timeline
1
Scoping Start
10/25/2022
2
Decision
08/2023 (Estimated)
3
Implementation
10/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| PacifiCorp New Service to GTN Pipeline | Decision Signed Date: 08/02/2023 |
| Forests | Fremont-Winema National Forest |
| Districts | Chiloquin Ranger District |
| Legal Land Description | T.34S., R.8E., Sec.1 |