Decision Memo Cancelled

Pacific Power Batch 57 Pole Replacement Project

Fremont-Winema National Forest Klamath, Oregon Chiloquin Ranger District

There is a need for Pacific Power to perform routine maintenance on power poles in the right of way.

Location

Project area is located on the Chiloquin Ranger District, Fremont-Winema National Forest.

Project timeline

1
Scoping Start
05/08/2023
2
Decision
09/2023 (Estimated)
3
Implementation
10/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsFremont-Winema National Forest
DistrictsChiloquin Ranger District
Legal Land DescriptionT. 34 S., R, 8 E., Sec. 31-33
Special use management