There is a need for Pacific Power to perform routine maintenance on power poles in the right of way.
Location
Project area is located on the Chiloquin Ranger District, Fremont-Winema National Forest.
Project timeline
1
Scoping Start
05/08/2023
2
Decision
09/2023 (Estimated)
3
Implementation
10/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Fremont-Winema National Forest |
| Districts | Chiloquin Ranger District |
| Legal Land Description | T. 34 S., R, 8 E., Sec. 31-33 |