The project places logjam structures in Pine Creek, Green Fork and Slide Creek to improve spawning and fish habitat.
Location
Pine Creek structures would be placed just north of Eagle Cliffs Resort. The Green Fork/Slide Creek structures would be placed just a few miles northeast of Sunset Campground.
Project timeline
1
Scoping Start
11/17/2010
2
Comment Period
03/28/2011
3
Decision
05/2011 (Estimated)
4
Implementation
07/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Instream Fish Habitat Restoration: Pine Creek, Slide Creek, Green Fork | Decision Signed Date: 05/05/2011 Legal Notice Date: 05/06/2011 |
| Forests | Gifford Pinchot National Forest |