Restore riparian areas and channel stability to recover viable populations of wild steelhead in Upper Trout Creek and its tributaries.
Location
Upper Trount Creek (170101051205) sixth field watershed.
Project timeline
1
Scoping Start
03/28/2002
2
Comment Period
04/16/2004
3
Decision
01/2005 (Estimated)
4
Implementation
06/2005 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Decision Notice: Upper Trout Creek Riparian, Stream Channel and Fish Passage Rehabilitation Project | Decision Signed Date: 01/10/2005 Legal Notice Date: 01/13/2005 |
| Forests | Gifford Pinchot National Forest |
| Districts | Mt Adams Ranger District |
| Legal Land Description | T. 4N, R. 6E, S. 1, 3, 4, 10, 11, 13, 14, 22, 23, & 24; T. 4N, R. 5E, S. 19, 25, & 30; and T. 5N, R. 6E, S. 34. |