The Cave-Bear Road Management project focuses on road decommissioning, closure and maintenance in Trout Lake Creek, Cave-Bear Creek, and Dry/Lost Creeks watersheds to restore failing roads and remove unneeded roads from the transportation system.
Location
Located in the Trout Lake Creek, Cave-Bear Creek and Dry/Lost Creek subwatersheds.
Project timeline
1
Scoping Start
06/17/2011
2
Comment Period
07/09/2013
3
Objection Period Start
07/09/2013
4
Decision
09/2013 (Estimated)
5
Implementation
07/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Road Maintenance; Watershed Improvements |
| Cave Bear Restoration Decision Notice | Decision Signed Date: 09/06/2013 Legal Notice Date: 09/12/2013 |
| Forests | Gifford Pinchot National Forest |
| Districts | Mt Adams Ranger District |
| Legal Land Description | Not Applicable |