A team of researchers are requesting a special use permit to conduct a series of geophysical experiments on the Forest. The objective is to obtain high-resolution data of the magmatic plumbing system underground the Cascades.
Location
Sites are distributed throughout the forest.
Project timeline
1
Scoping Start
07/19/2013
2
Comment Period
04/03/2014
3
Objection Period Start
05/16/2014
4
Decision
07/2014 (Estimated)
5
Implementation
07/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations; Research And Development |
| iMush Decision Notice | Decision Signed Date: 07/08/2014 Legal Notice Date: 07/08/2014 |
| Forests | Gifford Pinchot National Forest |
| Districts | Gifford Pinchot National Forest All Units |
| Legal Land Description | Not Applicable |