This project is proposed to develop off-channel aquatic and terrestrial wildlife habitat at two sites along the Cispus River corridor.
Location
T11N, R8E, Sections 10 and 18, Willamette Meridian.
Project timeline
1
Scoping Start
06/03/2014
2
Decision
11/2014 (Estimated)
3
Implementation
06/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Cispus Side Channel Restoration Projects | Decision Signed Date: 11/20/2014 |
| Forests | Gifford Pinchot National Forest |
| Districts | Cowlitz Ranger District |
| Legal Land Description | Not Applicable |