The project proposes to close or decommission roads or potions of roads; rehabilitate or block use of unauthorized routes; and conduct heavy road maintenance on roads that will remain open to the public.
Location
The project area is located north of Carson, WA, in the Rush Creek, Curly Creek, Big Creek, and Little Creek-Lewis River subwatersheds, all of which are in the Headwaters Lewis River watershed.
Project timeline
1
Scoping Start
09/14/2015
2
Comment Period
09/12/2016
3
Objection Period Start
01/13/2017
4
Decision
03/2017 (Estimated)
5
Implementation
06/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Road Maintenance; Road Improvements/Construction |
| Upper Lewis River Roads Project | Decision Signed Date: 03/13/2017 |
| Forests | Gifford Pinchot National Forest |
| Districts | Mt Adams Ranger District |
| Legal Land Description | T6N, R8E, Sections 6, 7, 18, 19; T6N, R7E, Sections 1, 3-5, 8-10, 12, 13, 15, 16, 22-24; T7N, R7E, Sections 1, 12-14, 23-26, 28-32, 35, 36; T7N, R8E, Sections 7, 8, 14-1718-21, 27-30, 33 |