Install approximately 2,500 ft. underground 7.2KV powerline at a depth of 42 inches. Project starts at junction box near junction of FR 23 & FR 55. Application was made by private landowner to extend the utility line to their property.
Location
Intersection of FR 23 and FR 55.
Project timeline
1
Scoping Start
08/15/2019
2
Decision
11/2019 (Estimated)
3
Implementation
11/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| LCPUD District FR-2300000 Powerline Line Extension Special Use Authorization | Decision Signed Date: 11/01/2019 |
| Forests | Gifford Pinchot National Forest |
| Districts | Cowlitz Ranger District |
| Legal Land Description | Not Applicable |