Environmental Assessment Completed

Pacific Crest National Scenic Trail Repair Upper Suiattle River

Mount Baker-Snoqualmie National Forest Snohomish, Washington Darrington Ranger District

Repair and relocation of segment of the Pacific Crest Trail using motorized equipment in the wilderness

Location

In Glacier Peak wilderness upper Suiattle valley

Project timeline

1
Scoping Start
02/15/2008
2
Comment Period
03/27/2009
3
Decision
05/2009 (Estimated)
4
Implementation
07/2009 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityTrail Management
Pacific Crest Trail Repair - Suiattle River CrossingDecision Signed Date: 05/15/2009 Legal Notice Date: 05/16/2009
ForestsMt Baker-Snoqualmie National Forest
DistrictsDarrington Ranger District
Legal Land DescriptionT31N, R13E; T31N, R14E