Repair and relocation of segment of the Pacific Crest Trail using motorized equipment in the wilderness
Location
In Glacier Peak wilderness upper Suiattle valley
Project timeline
1
Scoping Start
02/15/2008
2
Comment Period
03/27/2009
3
Decision
05/2009 (Estimated)
4
Implementation
07/2009 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| Pacific Crest Trail Repair - Suiattle River Crossing | Decision Signed Date: 05/15/2009 Legal Notice Date: 05/16/2009 |
| Forests | Mt Baker-Snoqualmie National Forest |
| Districts | Darrington Ranger District |
| Legal Land Description | T31N, R13E; T31N, R14E |