Reroute road 1106 to formerly abandoned roads, construct approximately 100 yards of new road, remove temporary bridge over Sulfur Creek, and decommission approximately 1/3 mile of existing road 1106.
Location
1 to 1.5 miles west of the south end of Baker Lake
Project timeline
1
Scoping Start
11/17/2009
2
Comment Period
06/16/2010
3
Decision
07/2010 (Estimated)
4
Implementation
08/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Road Improvements/Construction; Travel Management |
| Road 1106 Relocation | Decision Signed Date: 07/20/2010 Legal Notice Date: 07/21/2010 |
| Forests | Mt Baker-Snoqualmie National Forest |
| Districts | Mt Baker Ranger District |
| Legal Land Description | T 37 N, R 8 E, SW corner of section 25 |