Categorical Exclusion In Progress

PSE Foss River/Maloney Mtn Power Line Replacement

Mount Baker-Snoqualmie National Forest King, Washington Skykomish Ranger District

Puget Sound Energy proposes to replace 7 miles of failing power line buried along FSR 68 to Maloney Ridge and replace 1 mile of overland buried cable from Maloney to Sobieski. A temporary cable on the ground surface will be removed.

Location

Along FSR 68 to a comms site on Maloney Ridge, then overland along Maloney Ridge to Sobieski comms site.

Project timeline

1
NEPA Start Date
5/6/2024
2
Finding/Decision Date
5/14/2025

NEPA / regulatory detail

Categorical ExclusionUSDA-27d-USFS
Decision Signed Date5/14/2025