Repair two sites on the Diobsud Creek Road that were damaged when a portion of the roadway slid during a heavy rain event.
Location
Approximately 3 miles north of Marblemount, Washington
Project timeline
1
Scoping Start
05/21/2010
2
Comment Period
07/28/2010
3
Decision
08/2010 (Estimated)
4
Implementation
08/2011 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Improvements/Construction |
| Diobsud Road Repairs | Decision Signed Date: 08/31/2010 Legal Notice Date: 09/04/2010 |
| Forests | Mt Baker-Snoqualmie National Forest |
| Districts | Mt Baker Ranger District |
| Legal Land Description | Township 36 North, Range 11 east, Section 30 |