Environmental Assessment Completed

Harlan Creek Road Decommissioning

Mount Baker-Snoqualmie National Forest King, Washington Skykomish Ranger District

The proposed action is to decommission and remove from the Mt. Baker-Snoqualmie Forest Transportation System about 9.9 miles of road within the 6522 and 6525 road systems, within the Harlan and Johnson Creek drainages.

Location

Within the Johnson and Harlan Creek drainages of the lower Beckler River watershed.

Project timeline

1
Scoping Start
01/13/2011
2
Comment Period
01/18/2011
3
Decision
04/2012 (Estimated)
4
Implementation
06/2012 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Dispersed Recreation Mgmt.; Travel Management; Watershed Improvements; Wilderness Management
Harlan Creek Road Decommissioning ProjectDecision Signed Date: 04/16/2012 Legal Notice Date: 04/18/2012
ForestsMt Baker-Snoqualmie National Forest
DistrictsSkykomish Ranger District
Legal Land DescriptionSections 4 and 9, T 26N, R12E
Watershed managementRoad management