Relocate flood damaged, deteriorated, and slide-prone sections of the Middle Fork Trail between MP 3.04 and 3.83 to a bench out of the Middle Fork Snoqualmie River floodplain, decommissioning about 2,815 feet of damaged trail.
Location
Middle Fork Snoqualmie River watershed approximately 15 miles NE of the City of North Bend, WA
Project timeline
1
Scoping Start
02/13/2013
2
Comment Period
02/13/2013
3
Decision
08/2013 (Estimated)
4
Implementation
08/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| Middle Fork Trail #1003 Relocation Project (Milepost 3.04 to 3.83) | Decision Signed Date: 08/01/2013 |
| Forests | Mt Baker-Snoqualmie National Forest |
| Districts | Snoqualmie Ranger District |
| Legal Land Description | T24N, R10E, SW ¼ Section 25, SE ¼ SE ¼ Section 26, and NE ¼ NW ¼ Section 36 |