Supply sustainable forest products, and support the health and wildlife habitat values of forest stands, while meeting aquatic, recreational, and scenic objectives within the South Fork Snoqualmie watershed
Location
The project is within the South Fork Snoqualmie watershed, along the Interstate 90 corridor, approximately between mileposts 38 and 48.
Project timeline
1
Scoping Start
06/17/2014
2
Comment Period
02/24/2015
3
Objection Period Start
06/01/2015
4
Decision
08/2015 (Estimated)
5
Implementation
09/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Trail Management; Noxious Weed Treatments; Road Maintenance; Scenery Management; Watershed Improvements |
| Hansen Creek Vegetation Project DN-FONSI | Decision Signed Date: 08/03/2015 |
| Forests | Mt Baker-Snoqualmie National Forest |
| Districts | Snoqualmie Ranger District |
| Legal Land Description | Township 23 North (T23N), Range 9 East (R9E), Sections 34 and 35; T22N, R10E, Sec. 6-17; and T22N, R9E, Sec. 1, 2, 3 and 12. |