Issue a 20-year permit for the Upper Skagit Tribe to install and maintain gauging equipment on Skagit River tributary stream systems of Tenas Creek and Diobsud Creek.
Location
Skagit River tributary stream systems of the Mt. Baker and Darrington Districts on an existing bridge structure at Tenas Creek, and bolted to a rock within the stream corridor at Diobsud Creek.
Project timeline
1
Scoping Start
03/18/2016
2
Decision
04/2016 (Estimated)
3
Implementation
04/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Installation of Stream Gauge Equipment on Diobsud and Tenas Creeks | Decision Signed Date: 04/18/2016 |
| Forests | Mt Baker-Snoqualmie National Forest |
| Districts | Darrington Ranger District |
| Legal Land Description | T33N, R11E, Section 19 (Tenas Creek) and T36N, R11E, Section 30 (Diobsud Creek). |