Construct 5-10 large woody debris jams in the Beckler River to reconnect relic channels between the Beckler and South Fork Skykomish River floodplains, and to reconnect a side channel along the right-bank of the Beckler.
Location
Lower .4 mile of the Beckler River
Project timeline
1
Scoping Start
07/26/2019
2
Decision
09/2019 (Estimated)
3
Implementation
09/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Beckler River Confluence Restoration | Decision Signed Date: 09/27/2019 |
| Forests | Mt Baker-Snoqualmie National Forest |
| Districts | Skykomish Ranger District |
| Legal Land Description | T26N, R11E, Sec 25, NW 1/4 |