Install a septic system and drain field on Lot 145 to meet Pierce County requirements to phase out vault toilets.
Location
East of SR 410, near Greenwater, WA
Project timeline
1
Scoping Start
11/11/2019
2
Decision
09/2020 (Estimated)
3
Implementation
10/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Silver Springs Lot 145 Septic System SUP | Decision Signed Date: 09/24/2020 |
| Forests | Mt Baker-Snoqualmie National Forest |
| Districts | Snoqualmie Ranger District |
| Legal Land Description | Not Applicable |