The project proposes to construct and replace fences in the Frazier and Porcupine pastures on the Sunflower Allotment. The purpose and need is to protect anadromous fish, increase cattle dispersal and increase forage utilization in the uplands.
Location
FS Road 531 (Frazier Pasture), FS Road 58 (Sunflower Pasture)
Project timeline
1
Scoping Start
08/17/2012
2
Decision
01/2014 (Estimated)
3
Implementation
03/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Sunflower Allotment Fence Placement Project | Decision Signed Date: 01/16/2014 Legal Notice Date: 01/22/2014 |
| Forests | Ochoco National Forest |
| Districts | Paulina Ranger District |
| Legal Land Description | TRS: T15S, 26E, Sections 26, 27, 34, 35 (Frazier Pasture)/ T16S, R26E, Sections 13, 14 |