The proposal is to reduce forest density and fuels and conduct restoration activities.
Location
Southeast of Lookout Mountain on the Ochoco National Forest
Project timeline
1
NOI in Federal Register
03/04/2014
2
DEIS NOA in Federal Register
12/24/2015
3
FEIS NOA in Federal Register
04/04/2016
4
Objection Period Start
04/04/2016
5
Decision
07/2016 (Estimated)
6
Implementation
09/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements |
| Gap Landscape Restoration Project | Decision Signed Date: 07/05/2016 |
| Forests | Ochoco National Forest |
| Districts | Paulina Ranger District |
| Legal Land Description | Not Applicable |