The proposed project would implement dry forest restoration on approximately 15,810 acres in the project area.
Location
The project area is located on the Paulina Ranger District approximately 35 miles east of Prineville, Oregon.
Project timeline
1
NOI in Federal Register
01/13/2015
2
DEIS NOA in Federal Register
12/14/2018
3
FEIS NOA in Federal Register
07/19/2019
4
Objection Period Start
07/19/2019
5
Decision
12/2019 (Estimated)
6
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Watershed Improvements |
| Black Mountain Vegetation Management Project | Decision Signed Date: 12/16/2019 |
| Forests | Ochoco National Forest |
| Districts | Paulina Ranger District |
| Legal Land Description | Not Applicable |