The proposed project would authorize Zayo Group, LLC to construct, operate, and maintain approximately 104,145 linear feet of fiber optic underground conduit and cable system along Oregon State Highway 26 on National Forest lands.
Location
National Forest lands along Highway 26 between Prineville and Mitchell, Oregon.
Project timeline
1
Scoping Start
07/02/2019
2
Decision
02/2020 (Estimated)
3
Implementation
03/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Zayo Fiber Optic Project Decision Memo | Decision Signed Date: 02/28/2020 |
| Forests | Ochoco National Forest |
| Districts | Lookout Mountain Ranger District |
| Legal Land Description | Not Applicable |