The proposed project would authorize PGE to install fiber optics onto their existing Grizzly-Round Butte transmission line.
Location
The line is located north of the Grizzly Substation to Round Butte near Madras.
Project timeline
1
Scoping Start
09/13/2018
2
Decision
06/2019 (Estimated)
3
Implementation
09/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| PGE Fiber Optic Installation (Grizzly to Round) | Decision Signed Date: 06/11/2019 |
| Forests | Ochoco National Forest |
| Districts | Crooked River Natl Grassland |
| Legal Land Description | Not Applicable |