The proposed project would non-commercially thin the Blevins Seed Orchard to reduce density and competition and increase cone and seed production in remaining trees.
Location
Blevins Seed Orchard
Project timeline
1
Scoping Start
05/01/2020
2
Decision
06/2020 (Estimated)
3
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Blevins Seed Orchard Thinning Project | Decision Signed Date: 06/25/2020 |
| Forests | Ochoco National Forest |
| Districts | Lookout Mountain Ranger District |
| Legal Land Description | Not Applicable |