The Dodson Well Pipeline project would trench and bury 1.5 miles of pipeline to transport water from Dodson Well to a holding tank in the North Grizzly pasture of the Grizzly allotment.
Location
Grizzly allotment on the Crooked River National Grassland.
Project timeline
1
Scoping Start
07/17/2020
2
Decision
11/2020 (Estimated)
3
Implementation
11/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Dodson Well Pipeline | Decision Signed Date: 11/05/2020 |
| Forests | Ochoco National Forest |
| Districts | Crooked River Natl Grassland |
| Legal Land Description | Not Applicable |