The Forest is proposing to construct up to about 52 miles of trail with the primary use by mountain bikes but also open to other users. The proposed system is close to town and would provide a variety of difficulty levels.
Location
West end of the Ochoco NF, about 20 miles northeast of Prineville, Oregon.
Project timeline
1
Scoping Start
03/12/2021
2
Comment Period
11/17/2022
3
Objection Period Start
10/2024 (Estimated)
4
Decision
12/2024 (Estimated)
5
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Trail Management |
| Forests | Ochoco National Forest |
| Districts | Lookout Mountain Ranger District |
| Legal Land Description | Not Applicable |