Project timeline
1
NOI in Federal Register
10/21/2008
2
DEIS NOA in Federal Register
06/26/2009
3
FEIS NOA in Federal Register
06/01/2012
4
Decision
05/2012 (Estimated)
5
Implementation
08/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Noxious Weed Treatments |
| Invasive Plant Treatment ROD Part 1 | Decision Signed Date: 12/05/2007 (FS Withdrawn) Legal Notice Date: 01/04/2008 |
| Invasive Plant Treatments | Decision Signed Date: 05/02/2012 Legal Notice Date: 06/01/2012 |
| Forests | Deschutes National Forest; Ochoco National Forest |
| Districts | Deschutes National Forest All Units; Ochoco National Forest All Units |