Two electronic vehicle charging machines will be installed at the Crooked River Day Use Area parking lot.
Location
T 12 S, R 12 E, Section 2
Project timeline
1
Scoping Start
11/09/2022
2
Decision
01/2023 (Estimated)
3
Implementation
01/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| EV Charging Station State Pilot Project at Cove Palisades State Park | Decision Signed Date: 01/05/2023 |
| Forests | Ochoco National Forest |
| Districts | Crooked River Natl Grassland |
| Legal Land Description | Not Applicable |