authorizing term permits for fiber, electric, and sewer utilities to the administrative site, including modifications to existing lines.
Location
Prineville, Oregon
Project timeline
1
Scoping Start
03/01/2023
2
Decision
03/2023 (Estimated)
3
Implementation
03/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lamonta Compound Administrative Site Utilities | Decision Signed Date: 03/13/2023 |
| Forests | Ochoco National Forest |
| Districts | Ochoco National Forest All Units |
| Legal Land Description | Township 14 South, Range 16 East, Section 31, Willamette Meridian |