Project timeline

1
Scoping Start
09/15/2006
2
Comment Period
09/15/2006
3
Decision
06/2011 (Estimated)
4
Implementation
06/2011 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFacility Improvements/Construction; Facility Maintenance
Hillcrest ConveyanceDecision Signed Date: 06/15/2011 Legal Notice Date: 06/18/2011
ForestsSiuslaw National Forest
DistrictsSiuslaw National Forest All Units
Legal Land DescriptionT.18S., R.10W., portions of Sections 2, 11