Issue 9 authorizations to replace existing and/or expired authorizations for: water transmission lines, roads, and livestock areas.
Location
Various locations within the Central Coast Ranger District--Oregon Dunes National Recreation Area.
Project timeline
1
Scoping Start
09/30/2013
2
Decision
12/2014 (Estimated)
3
Implementation
01/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Special Use Authorizations Multi-Year Permits | Decision Signed Date: 12/22/2014 |
| Forests | Siuslaw National Forest |
| Districts | Central Coast Ranger District/Oregon Dunes National Recreation Area |
| Legal Land Description | Not Applicable |