Tillamook PUD is requesting an amendment to provide fiber optic communication to the electrical substation. The cable would be laid under an existing road for a lenth of approximately 120 feet.
Location
Located about half a mile east of Hebo Work Camp along Cedar Creek Road.
Project timeline
1
Scoping Start
05/17/2023
2
Decision
06/2023 (Estimated)
3
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Area Management |
| Tillamook Public Utility District Special Use Permit | Decision Signed Date: 06/15/2023 |
| Forests | Siuslaw National Forest |
| Districts | Hebo Ranger District |
| Legal Land Description | Not Applicable |