This project will maintain stable elk herds, reduce fuel loads and stand density conditions, providing wood products (22 MMBF) to the local community by thinning about 1370 acres. Road construction/reconstruction will also occur.
Location
Fish Creek Watershed, Diamond Lake RD
Project timeline
1
Scoping Start
03/15/2005
2
Comment Period
10/25/2005
3
Decision
03/2006 (Estimated)
4
Implementation
04/2006 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Road Improvements/Construction; Timber Sales (Green) |
| Wapiti Timber Sale Project | Decision Signed Date: 03/28/2006 Legal Notice Date: 03/30/2006 |
| Forests | Umpqua National Forest |
| Districts | Diamond Lake Ranger District |
| Legal Land Description | Portions of T26S, R3E; T27S, R3E; T28S, R3E; T27S, R4E; T28S, R4E. |