Environmental Assessment Completed

Steamboat Watershed Aquatic Connectivity Project

Umpqua National Forest Douglas, Oregon North Umpqua Ranger District

Provide passage for aquatic organisms and 100 year flow events at stream crossings in the Steamboat Creek Watershed.

Location

Steamboat Creek 5th field watershed

Project timeline

1
Scoping Start
08/08/2008
2
Comment Period
04/17/2009
3
Decision
05/2009 (Estimated)
4
Implementation
08/2009 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityWatershed Improvements
Steamboat Aquatic Passage and Restoration ProjectDecision Signed Date: 05/26/2009 Legal Notice Date: 06/02/2009
ForestsUmpqua National Forest
DistrictsNorth Umpqua Ranger District
Wildlife, fish, rare plantsWatershed management