Decision Memo Completed

Donegan Prairie Restoration Project

Umpqua National Forest Douglas, Oregon Tiller Ranger District

Restore meadows by removing encroaching conifers and treat fuels in meadows and adjacent forests.

Location

Donegan Prairie, Squaw Creek 6th Field, Jackson Creek 5th Field Watersheds

Project timeline

1
Scoping Start
04/07/2012
2
Comment Period
04/07/2012
3
Decision
06/2012 (Estimated)
4
Implementation
07/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Species Habitat Improvements; Watershed Improvements
Decision Memo for the Donegan Prairie Restoration ProjectDecision Signed Date: 06/08/2012 Legal Notice Date: 06/17/2012
ForestsUmpqua National Forest
DistrictsTiller Ranger District
Legal Land DescriptionT30S R2E Secs 31 and 32
Fuels managementWatershed managementSpecial area managementVegetation management (other than forest products)