This project is designed to improve stand health and diversity, improve fire resiliency, provide forest products and maintain/restore meadow habitats.
Location
Project Area is within the upper portion of the Sharps Creek Watershed.
Project timeline
1
Scoping Start
12/18/2014
2
Comment Period
08/08/2017
3
Objection Period Start
03/20/2018
4
Decision
07/2019 (Estimated)
5
Implementation
09/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Noxious Weed Treatments; Road Maintenance; Timber Sales (Green); Watershed Improvements |
| Calapooya Divide Integrated Project | Decision Signed Date: 07/12/2019 |
| Forests | Umpqua National Forest |
| Districts | Cottage Grove Ranger District |
| Legal Land Description | Not Applicable |