Decision Memo Completed

Rock Removal Authorization from Slide Creek and Beckley Thomas Quarries

Umpqua National Forest Douglas, Oregon Diamond Lake Ranger District

FERC ordered Pacific Power to relocate the intake and bolster the Toketee Dam with apprx 85,000 cyds of material. Pacific Power needs authorization to acquire the material from Slide Creek and Beckley Thomas Quarries.

Location

Slide Creek and Beckley Thomas Quarries near North Umpqua River corridor via State Route Hwy 138

Project timeline

1
Scoping Start
03/01/2021
2
Decision
04/2021 (Estimated)
3
Implementation
04/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Rock Removal Authorization from Slide Creek and Beckley Thomas QuarriesDecision Signed Date: 04/20/2021
ForestsUmpqua National Forest
DistrictsDiamond Lake Ranger District
Legal Land DescriptionTownship 26 South, Range 3 East, Section 13, NW NW 1/4; Township 27 South, Range 4 East, Section 6, NW 1/4 Will Meridian
Special use managementMinerals and geology