This project would approve the authorization of three new special use permits (SUP) and changes to one current SUP at existing telecommunication sites on the Diamond Lake Ranger District.
Location
T26S, R4E, Section 28; T27S, R6E, Section 32; T27s, R6E, Section 9
Project timeline
1
Scoping Start
07/01/2022
2
Decision
07/2022 (Estimated)
3
Implementation
08/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Diamond Lake Telecommunication Site Special Use Permit Authorization | Decision Signed Date: 07/21/2022 |
| Forests | Umpqua National Forest |
| Districts | Diamond Lake Ranger District |
| Legal Land Description | Not Applicable |