Issuance of new special use permit to build access route to property. Road apprx 1000 feet in length stemming from NFS route 3113-114. Gated to prevent public use.
Location
Road would stem off an existing National Forest System route 3113-114 located approximately 1.5 miles southeast of Tiller.
Project timeline
1
Scoping Start
10/09/2024
2
Decision
11/2024 (Estimated)
3
Implementation
11/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Elk Creek Parcel Access Route SUP | Decision Signed Date: 11/15/2024 |
| Forests | Umpqua National Forest |
| Districts | Tiller Ranger District |
| Legal Land Description | T 30 South R 02 West Section 35 |